Loading
Newsletter Sign up

Upcoming Events

Nov 9, 2009
6:00 pm, Monday
City Commission Meeting
Commission Meeting Room
New City Hall, 121 N. Rouse
PDF

Nov 3-17, 2009
3:45-5:15 p.m.
After School Class
Lindley Center
1102 E. Curtiss,
Learn More..

Nov 19, 2009
4:00-7:00 p.m.
Shred Your Identiy
Law and Justice Center
615 South 16th Ave.,
PDF    RTF


 

 Bozeman video

Downtown Bozeman at Night

City of Bozeman Road Report Updates


Mendenhall Street

Date: Nov 3-5

Locations: Willson to 3rd

Road Information: Mendenhall Street to be closed beginning Nov. 3rd from Willson to 3rd for installation of a water service line for the Ketterer Building at 35 N. Grand Ave. Work is expected to take 2 days. Traffic will be detoured at Willson Ave.

Contractor: RLS Construction 282-9061

S. Willson Ave.

For: Beginning Nov 2

Location: S. Willson Ave. near the intersection of Lincoln Street

Road Information: North Western Energy anticipates gas line work on S. Willson Ave. near the intersection of Lincoln Street beginning Monday, Nov. 2nd . No closures or detours are anticipated, but all traffic will be diverted to the west side of the road, and parking will be restricted in the work zone.

Contact: Mark Holley, 582-4639

Baxter Lane

For: Oct 5, 2009

Project Description: Baxter Lane will be closed for utility installation beginning October 5 and will remained closed until the installation is completed. The closure begins at the intersection of Baxter Lane and Sacco and the Holiday Inn entryway will be closed. Traffic to and from the Hampton Inn will be allowed.

Contact Information: Sime Construction – 582-9841

2009 water renovations

For: October 25-31, 2009

Road Information:  Work is substantially complete on Willson Avenue and all areas west of 7th Ave (Lamme St from 8th Ave. to 10th Ave;  9th Ave from Main St. to Lamme St.;  8th Ave from Lamme St. to Beall St.)  Roads are now open in these areas.  There will be a future period of traffic control, but no road closure on westbound lanes of Main St. to remove a temporary asphalt patch and replace it with permanent hot mix pavement. This work is weather dependent and is not currently scheduled but should be completed within a few hours when it is done.

Lamme St. from 7th Ave. to Grand Ave. (with the exception of the 3rd Avenue intersection) and 5th Ave. from Main St. to Beall St.(with the exception of the Mendenhall intersection) are currently closed.  All underground pipe installation has been completed in these areas but pavement reconstruction still needs to be done.  Paving of Lamme St. is planned for mid-week, weather permitting. At that time the 3rd Ave. intersection will be closed for one day only.  Paving of 5th Ave. is planned for late in the week or early the following week, weather permitting.  At that time Mendenhall St. will be closed for one day only. As paving is completed

Contact Information: City Engineering Office – 582-2280

SOUTH 19TH

For: October 23 - 30, 2009

Project Description: S. 19th Avenue Construction Project

Road Information: Rainy, cold weather early in the week delayed the paving progress on S. 19th which, in turn, delayed other aspects of the project. Knife River aims to wrap up work for the season by mid-November.

Paving between Babcock and Dickerson was scheduled to be completed on Monday, Oct. 19, but  was delayed until Wednesday, Oct. 21. All paving and sidewalk work for the project has now been completed. No delays or detours are expected for the remainder of the project.

The traffic light installation at the intersection of S. 19th and W. Koch is scheduled to be completed Nov. 4. Crews are working hard to complete median curb-cap installation and top soiling. Once those are completed, the project will wrap up for the year.

Chip sealing and final permanent pavement markings will occur next spring.

Contact Information: Knife River – Steve Baeth or Josh Walter – 388-6832 x 0 or visit www.19thbozeman.com

SOUTH BOZEMAN

Information: South Bozeman has been temporarily closed to traffic from Babcock to Main due to a sink hole in the street.

Contact Information: R & R TAYLOR CONSTRUCTION, INC. 587-4451